Standard Concrete Assemblies
    • Dark
      Light
    • PDF

    Standard Concrete Assemblies

    • Dark
      Light
    • PDF

    Article summary

    Overview 

    This help article will help the reader in the use of the STACK concrete catalog, whether a veteran in the trade or a new employee with no construction experience. The STACK concrete catalog contains assemblies for all sorts of flatwork and foundation structures. Flatwork assemblies do not contain rebar items, so adding an additional rebar assembly may be necessary. Rebar-only assemblies are available that mimic a concrete counterpart. Not only are they good for rebar-only contractors, but also can be added for more complicated rebar configurations.


    Terminology 

    We recognize that different regions use different terms for their trades. This list should help you better understand the choices STACK assemblies offer.

    • Footer, Beam, Stem Wall – As far as STACK assemblies are concerned, these terms are interchangeable. All refer to structures in the foundation with length, width, and depth measured using a Volume 3D or Linear takeoff.
    • Column, Pier – these terms refer to concrete that typically has a larger vertical component, whether into the ground or supporting part of the structure above.
    • Continuous Rebar – This is rebar that runs along the length of the footer or beam
    • Cages, Stirrups – These terms refer to rebar bent into a circle or rectangle or U-shape surrounding and supporting vertical or continuous rebar.
    • Horizontal Rebar - this refers to two different types of rebar, depending on the assembly. In the “Concrete Wall – 3D” assembly it refers to rebar that runs along the length of the wall and spaced evenly going up the wall. In footer and beam assemblies, horizontal rebar sits perpendicular to the continuous rebar with length approximately equal to the width of the footing or beam. This type of rebar is sometimes called transverse rebar or cross-bridging.
    • Bar Lap Count – the number of rebar diameters needed to make up the splice length. This is often confused with the splice length itself. The equation to determine this number is Rebar Diameter X Bar Lap Count = Splice Length. For example, if we have #4 rebar and a 2 foot splice length, our equation is .5 X Bar Lap Count = 24 then Bar Lap Count = 24/.5 = 48.

    Table of contents 

    03 30 00 - Rebar

    03 31 00 - Foundation

    03 33 13 - Slab On Grade

    03 33 19 - Elevated Concrete

    03 47 00 - Site Cast Concrete

    32 16 00 - Curbs & Gutters

    Concrete Formwork - 2D
    Concrete Formwork - Linear


    03 30 00 - Rebar

    Corner Rebar

    Summary: This assembly is designed for a Count takeoff and can be used for corners, T intersections and X intersections. Currently, rebar is only available by the linear foot in this assembly.

    Variables:

    • Number Of Rebar Needed - Enter the number of pieces of rebar needed for each count
    • Length Of Rebar Need In Feet - Enter the length of each piece of rebar

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Rebar for "L Intersection" Corner - Uses both variables and takeoff total for calculations
    • Rebar for "T Intersections" - Uses both variables and takeoff total for calculations and multiples the result by 2
    • Rebar for "+ Intersections" - Uses both variables and takeoff total for calculations and multiples the result by 4

    Rebar For Beam - Linear

    Summary: This assembly is based on a Linear takeoff and yields continuous rebar, rebar stirrups, tie wire and labor

    Variables:

    • Stirrup Spacing In - used to calculate stirrup rebar
    • Beam Width In - width of the concrete, used to calculate stirrup rebar
    • Continuous Rebar Count - how many pieces or rebar run along the length of the beam
    • Rebar Waste 1 to 100 - enter a number as a percentage of waste you want added
    • Rebar Stock Length Feet - the length of the rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Crew Production Lbs Per Hour - used to calculate labor hours
    • Cont Bar Size - the number of rebar you chose from the item group (3, 4, 5, etc.), used for calculating tie wire
    • Stirrup Bar Size - the number of rebar you chose from the item group (3, 4, 5, etc.), used for calculating tie wire
    • Beam Depth In - depth of the concrete, used to calculate stirrup rebar

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire - by the roll, calculated using all variables

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Continuous Rebar - rebar by the pound or linear foot
    • Rebar Stirrups - rebar by the pound or linear foot
    • Reinforcing Crew For Cont. Bars - yielding crew hours

    Rebar For Column, Round - Count

    Summary: This assembly is designed for rebar for round columns, both vertical and cages. You could also use this for round piers that require the same rebar configuration. It is designed for a count takeoff.

    Variables:

    • Column Diameter In – Enter the diameter of the column in inches.
    • Column Height In – Enter the height (vertical dimension) of the column in inches, can also be the depth if this is a pier.
    • Vertical Rebar Count – Enter the number of pieces of rebar that run vertically in the column.
    • Rebar Waste 1 to 100 – Enter a percentage waste factor for rebar.
    • Cage Rebar Spacing In – Enter the spacing of cages in inches.
    • Anchors Per Column – The number of anchor bolts required per column.
    • Vert Bar Size – Used to calculate tie wire and rebar labor crew, enter the vertical rebar’s number (3, 4, 5, etc.).
    • Cage Bar Size - Used to calculate tie wire and rebar labor crew, enter the cage rebar’s number (3, 4, 5, etc.).
    • Crew Production Lbs Per Hr – For your rebar placement crew, enter the amount of rebar they can place in pounds.

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions.

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
    • Choose Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
    • Choose Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
    • Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total

    Rebar For Column, Square - Count (2021)

    Summary: This assembly is designed for rebar in rectangular concrete columns as vertical and cage rebar.

    Variables:

    • Column Height In – the column’s vertical dimension, whether height or depth, entered in inches
    • Vertical Rebar Count – how many pieces of rebar are placed vertically in the column
    • Rebar Waste 1 To 100 – enter a percentage waste factor for rebar
    • Cage Rebar Spacing In – enter the spacing of your cages as they go up the column in inches
    • Column Width In – one of the horizontal dimensions of the column
    • Column Length In – the other horizontal dimension of the column
    • Vert Bar Size - enter the vertical rebar's number, used for calculating tie wire
    • Cage Bar Size - enter the cage rebar's number, used for calculating tie wire
    • Anchors Per Column - how many anchor bolts you need per column

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete – Items for structural concrete from 2500 to 5500 PSI, calculated based on takeoff total and column dimension variables
    • Form Material – Contains sonotube items from 8” to 48” diameter
    • Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
    • Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
    • Formwork Crew In Columns Per Hour – Choose a forming crew, total hours calculated based on takeoff total and form production variable
    • Concrete Crew In Cubic Yards Per Hour – Choose a concrete placement crew, total hours calculated based on total concrete and place production variable
    • Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
    • Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total

    Rebar For Concrete Wall - Linear

    Summary: This assembly is designed for a Linear takeoff.

    Variables:

    • Wall height In - enter the height of the concrete, used to calculate vertical and horizontal rebar
    • Rebar Waste 1 To 100 - enter a percentage waste factor for rebar
    • Vertical Rebar Spacing In - enter rebar spacing in inches
    • Horizontal Rebar Spacing In - enter rebar spacing in inches
    • Rebar Mat Count - how many mats of rebar are to be installed in the wall
    • Rebar Stock Length Feet - the length of the rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Vert Bar Size - the number of the rebar you chose
    • Horz Bar Size - the number of the rebar you chose
    • Crew Production Lbs Per Hr - the productivity of the labor crew you chose

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the wall dimensions

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Vertical Rebar Reinforcing - choose rebar by the foot or pound, length of each will be the wall height, the total considers linear takeoff and rebar spacing variable
    • Horizontal Rebar Reinforcing - choose rebar by the foot or pound, length will be figured using the wall height, linear takeoff, spacing variable and bar lap count
    • Rebar Crew In Pounds Per Hour - choose a labor crew whose productivity is specified in the associated variable

    Rebar For Continuous Footer - Linear

    Summary: This assembly is designed for a Linear takeoff and may work with any concrete takeoff whose primary dimension is length, e.g. beams, stem walls, footings, thickened edges.

    Variables:

    • Footer Width In - width of the concrete, used to figure horizontal/transverse rebar
    • Continuous Rebar Count - how many runs of rebar go along the length of the concrete
    • Horizontal Rebar Spacing In - used to calculate horizontal/transverse rebar
    • Vertical Dowel Spacing In - used to calculate vertical dowels
    • Vertical Dowel Length Ft - total length of each vertical dowel, including hooks, bends, etc.
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Rebar Stock Length Feet - the length of the rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Cont Bar Size - the number of the rebar you chose
    • Cross Bar Size - the number of the rebar you chose
    • Vert Dowel Size - the number of the rebar you chose
    • Crew Production Lbs Per Hr - the productivity of the labor crew you chose
    • Stirrup Spacing In Feet - used to calculate stirrup rebar
    • Stirrup Length In Feet - total length of each stirrup

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the footing dimensions

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Continuous Rebar Reinforcing - choose rebar by the pound or linear foot, calculated using count variable, takeoff measurement and bar lap count
    • Choose Rebar Cross-Bridging - choose rebar by the foot or pound, calculated using takeoff length and horizontal/transverse/cross variables
    • Add Rebar Chairs - calculated at one chair per continuous rebar run and every 4 feet
    • Add Vertical Dowels (if used) - choose rebar by the foot or pound, calculated using takeoff length and vertical dowel variables
    • Rebar Crew In Pounds Per Hour - choose a labor crew whose productivity is specified in the associated variable
    • Rebar For Stirrups (if used) - Choose rebar by the foot or pound, calculated using takeoff length and stirrup variables

    Rebar For Pier Footer - Count

    Summary: This assembly is designed for a count takeoff. It is to be used for footings that have rebar in a "grid" layout with options for a top and/or bottom layer.

    Variables:

    • Footer Width Ft - One horizontal dimension of the footing
    • Footer Height Ft - the other horizontal dimension of the footing
    • Rebar Count - how many pieces of rebar go one way, this assumes both ways have the same count, so if they are different, an average count should suffice
    • Top Bar Size - the number of the rebar chosen
    • Bot Bar Size - the number of the rebar chosen
    • Crew Production Lbs Per Hr - the productivity of the labor crew chosen

    Required Items:

    • 16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the footing dimensions

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Rebar Each Way @ Bottom - Choose rebar by the foot or by the pound, calculated using the footing dimensions and rebar count
    • Rebar Each Way @ Top - Choose rebar by the foot or by the pound, calculated using the footing dimensions and rebar count
    • Rebar Crew In Pounds Per Hr - choose a labor crew whose productivity is specified in the associated variable

    Rebar For Slab - Area

    Summary: This is based on an Area-type takeoff and may be used for any concrete flatwork.

    Variables:

    • Rebar Waste 1 To 100 - Enter a percentage waste factor
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Rebar Spacing In - the "on-center" number, spacing of the rebar in inches
    • Bar Size - the number of the rebar you chose
    • Crew Production Lbs Per Hr - productivity of the crew chosen
    • Reinforcing Chairs Sq Ft Per Each - square foot spacing of rebar chairs

    Required Items:

    • 16 Gauge Tie Wire - based on the number of your rebar chosen in variables and the takeoff dimensions

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Rebar Reinforcing (On Center Each Way) - choose rebar in feet or pounds
    • Reinforcing Crew - choose a crew with productivity rate in the related variable
    • Choose Rebar Chairs - chairs will be calculated based on total takeoff area and spacing variable

    Rebar For Spread Footer - Area

    Summary: This assembly is designed for an Area-type takeoff and will work for rebar in a "grid" pattern with one or two mats

    Variables:

    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Sqft Per Rebar Chair - square foot spacing of rebar chairs
    • Top Rebar Spacing In - the on-center number for the top mat of rebar
    • Bottom Rebar Spacing In - the on-center number for the bottom mat of rebar
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - Click here for a description
    • Bot Bar Size - the number of rebar chosen
    • Top Bar Size - the number of rebar chosen
    • Crew Production Lbs Per Hr - productivity of the crew chosen

    Required Items:

    • 16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the takeoff dimensions

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Bottom Rebar Reinforcing (On Center Each Way) - choose rebar by the foot or pound, calculated using the takeoff total, spacing variable, bar lap count and stock length
    • Top Rebar Reinforcing (On Center Each Way) - choose rebar by the foot or pound, calculated using the takeoff total, spacing variable, bar lap count and stock length
    • Add Rebar Chairs (sf per each chair) - calculated using takeoff measurement and spacing variable
    • Rebar Crew Production - choose a labor crew, calculated by takeoff value and productivity variable

    03 31 00 - Foundation

    Concrete Column/Pier Footer - Count

    Summary: This assembly is designed for a Count takeoff and works for rectangular concrete structures. Rebar will be one or two mats in a grid pattern.

    Variables:

    • Footer Width Ft - One of the horizontal dimensions of the column/pier
    • Footer Height Ft - The other horizontal dimension
    • Footer Depth In - the vertical dimension of the column/pier
    • Concrete Waste 1 To 100 - enter a percentage waste factor for the concrete
    • Rebar Count - how many pieces of rebar go "one way"
    • Anchor Bolts Per Column - necessary if using anchor bolts
    • Excavate Production Cy Per Hr - productivity rate of the excavation crew you choose
    • Place Production Cy Per Hr - productivity rate of the concrete crew you choose
    • Depth To Top Of Footer In - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
    • Top Bar Size - the number (size) of rebar on the top mat
    • Bot Bar Size - the number (size) of rebar on the bottom mat
    • Crew Production Lbs Per Hr - productivity rate of the rebar crew you choose

    Required Items:

    • Foundation, Square Feet - total square footage viewed from the top
    • Footer Count - takeoff count total
    • Excavation Quantity - total amount excavated equaling the volume of concrete plus volume above determined by "Depth To Top Of Footer In" variable
    • 16 Gauge Tie Wire - determined by rebar calculations and bar size variables

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Concrete - calculated using the takeoff total and dimension variables
    • Rebar @ Bottom - the bottom mat of rebar calculated using rebar count and horizontal concrete dimension variables
    • Rebar @ Top - the top mat of rebar calculated using rebar count and horizontal concrete dimension variables
    • Anchor Bolts - based on takeoff total and anchor bolt variable
    • Excavation Crew In Cubic Yards Per Hour - calculated using excavation volume and productivity variable
    • Concrete Placing Crew - calculated using concrete volume and productivity variable
    • Rebar Crew In Pounds Of Steel Per Hour - calculated using rebar total and productivity variable

    Concrete Column, Round - Count 

    Summary: This assembly is designed for round columns requiring sonotube forms with vertical and cage rebar. You could also use this for round piers that require the same rebar configuration, not selecting a form item. It is designed for a count takeoff.

    Variables:

    • Column Diameter In – Enter the diameter of the column in inches.
    • Column Height In – Enter the height (vertical dimension) of the column in inches, can also be the depth if this is a pier.
    • Concrete Waste 1 to 100 – Enter a percentage waste factor for concrete.
    • Vertical Rebar Count – Enter the number of pieces of rebar that run vertically in the column.
    • Rebar Waste 1 to 100 – Enter a percentage waste factor for rebar.
    • Cage Rebar Spacing In – Enter the spacing of cages in inches.
    • Form Production Column Per Hr – For your forming labor crew, enter the number of columns your forming crew can install in one hour.
    • Place Production Cy Per Hr – For your concrete placement crew, enter the amount of concrete they can place in cubic yards in one hour.
    • Anchors Per Column – The number of anchor bolts required per column.
    • Vert Bar Size – Used to calculate tie wire and rebar labor crew, enter the vertical rebar’s number (3, 4, 5, etc.).
    • Cage Bar Size - Used to calculate tie wire and rebar labor crew, enter the cage rebar’s number (3, 4, 5, etc.).
    • Crew Production Lbs Per Hr – For your rebar placement crew, enter the amount of rebar they can place in pounds.

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions.
    • Poured Columns, Round – a Summary type item that simply reflects the takeoff total.

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete – Items for structural concrete from 2500 to 5500 PSI, calculated based on takeoff total and column dimension variables
    • Form Material – Contains sonotube items from 8” to 48” diameter
    • Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
    • Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
    • Formwork Crew In Columns Per Hour – Choose a forming crew, total hours calculated based on takeoff total and form production variable
    • Concrete Crew In Cubic Yards Per Hour – Choose a concrete placement crew, total hours calculated based on total concrete and place production variable
    • Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
    • Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total

    Concrete Column, Square - Count (2021) 

    Summary: This assembly is designed for rectangular concrete columns with vertical and cage rebar and plywood forms.

    Variables:

    • Column Height In – the column’s vertical dimension, whether height or depth, entered in inches
    • Concrete Waste 1 To 100 – enter a percentage waste factor for concrete
    • Vertical Rebar Count – how many pieces of rebar are placed vertically in the column
    • Rebar Waste 1 To 100 – enter a percentage waste factor for rebar
    • Cage Rebar Spacing In – enter the spacing of your cages as they go up the column in inches
    • Column Width In – one of the horizontal dimensions of the column
    • Column Length In – the other horizontal dimension of the column
    • Form Production SF Per Hour – how many square feet of forming can your forming crew place in an hour
    • Place Production CY Per Hour – how many cubic yards of concrete your placing crew can do in an hour
    • Anchors Per Column - how many anchor bolts you need per column

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions
    • Poured Columns, Round – a Summary type item that reflects the takeoff total

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete – Items for structural concrete from 2500 to 5500 PSI, calculated based on takeoff total and column dimension variables
    • Form Material – Contains sonotube items from 8” to 48” diameter
    • Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
    • Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
    • Formwork Crew In Columns Per Hour – Choose a forming crew, total hours calculated based on takeoff total and form production variable
    • Concrete Crew In Cubic Yards Per Hour – Choose a concrete placement crew, total hours calculated based on total concrete and place production variable
    • Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
    • Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total

    Concrete Grade Beam - 3D

    Summary: This assembly requires a Volume 3D takeoff. It is designed for concrete structures with length as the primary dimension with continuous rebar and stirrups.

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Stirrup Spacing In - used to calculate stirrup rebar
    • Beam Width In - the other horizontal dimension of the footing, used to calculate excavation totals and stirrup rebar
    • Beam Depth In - the vertical dimension of the beam, used to calculate excavation totals and stirrup rebar
    • Continuous Rebar Count - how many runs of rebar go along the length of the beam
    • Formed Side Count - how many sides of the beam need forms
    • Form Production Lf Per Hr - productivity rate for the forming crew chosen
    • Place Production Cy Per Hr - productivity rate for the concrete crew chosen
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Excavation Width In - width of trench to be excavated
    • Excavation Depth In - depth of trench to be excavated
    • Excavate Production Cy Per Hr - productivity rate for the excavation crew chosen
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Cont Bar Size - the number of the rebar chosen
    • Stirrup Bar Size - the number of the rebar chosen
    • Crew Production Lbs Per Hr - productivity rate for the rebar crew chosen

    Required Items:

    These items will be added without having to choose them

    • Grade Beam Linear Feet - summary item reflecting the linear component of your takeoff
    • 16 Gauge Tie Wire - calculated using the rebar totals and size variables
    • Excavation Quantity - total amount to be excavated

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on takeoff volume
    • Continuous Rebar - by the foot or pound, based on linear footage from the takeoff, bar lap count and continuous count variable
    • Rebar Stirrups - choose rebar by the foot or pound, calculated using beam dimensions and spacing variable
    • Add Form Panels - based on beam dimensions and count variable
    • Choose Excavation Crew - requires the productivity variable to calculate
    • Choose Forming Crew - requires the productivity variable to calculate
    • Choose Concrete Placing Crew - requires the productivity variable to calculate
    • Rebar Crew In Pounds Of Steel - requires the productivity variable to calculate

    Concrete Spread Footer - 2D

    Summary: This assembly requires a Volume 2D takeoff and offers 1 or 2 mats of rebar.

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Sqft Per Rebar Chair - the square foot spacing of rebar chairs
    • Top Rebar Spacing In - your on center number in inches
    • Bottom Rebar Spacing In - your on center number in inches
    • Depth To Top Of Footer Inches - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
    • Excavate Production Cy Per Hr - the productivity rate of the crew chosen
    • Place Production Cy Per Hr - the productivity rate of the crew chosen
    • Anchor Bolt Count - number of bolts per footer
    • Rebar Mat Count - this variable is not currently used
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Bot Bar Size - the number of the rebar you chose
    • Top Bar Size - the number of the rebar you chose
    • Crew Production Lbs Per Hr - the productivity rate of the crew chosen

    Required Items:

    These items will be added without having to choose them

    • Foundation, Square Feet - summary item showing the area of the footing from the top
    • 16 Gauge Tie Wire - calculated using the rebar totals and size variables
    • Excavation Quantity - calculated using the concrete total, takeoff area and depth to top of footing variable

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on takeoff total volume
    • Bottom Rebar Reinforcing (On Center Each Way) - choice of rebar by the foot or pound, giving you one of the mats of rebar in the footing
    • Top Rebar Reinforcing (On Center Each Way) - choice of rebar by the foot or the pound, giving you one of the mats of rebar in the footing
    • Add Rebar Chairs (sf per each chair) - calculated using the area component from your takeoff and the spacing variable
    • Excavation Crew (depth to footer & cy per hour) - requires the productivity variable to calculate
    • Crew To Place Concrete - requires the productivity variable to calculate
    • Choose Anchor Bolts - total count of footers times the anchor bolt variable
    • Rebar Crew In Pounds Of Steel Per Hour - requires the productivity variable to calculate

    Concrete Wall - 3D

    Summary: This assembly requires a Volume 3D takeoff and yields vertical and horizontal rebar

    Variables:

    • Wall Height In - the height of the concrete wall, used to calculate rebar
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Waler Runs - used for calculating waler brackets and snap ties
    • Vertical Rebar Spacing In - on center spacing for vertical rebar along the length of the wall
    • Horizontal Snap Tie Spacing In - on center spacing of snap ties along the length of the wall
    • Horizontal Rebar Spacing In - on center spacing of horizontal rebar going up the wall
    • Form Production Sf Per Hr - the productivity rate of the crew chosen
    • Place Production Cy Per Hr - the productivity rate of the crew chosen
    • Linear Ft Per Anchor Bolt - anchor bolt spacing
    • Rebar Mat Count - how many mats or "grids" of rebar present in the wall
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Vert Bar Size - the number of the rebar you chose
    • Horz Bar Size - the number of the rebar you chose
    • Crew Production Lbs Per Hr - the productivity rate of the crew chosen

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire - calculated using the rebar totals and size variables
    • Poured Wall, Linear Feet - summary item reflecting the linear component of the takeoff
    • Poured Wall, Square Feet - summary item reflecting the square footage of the wall
    • A16 Omni Wedge - based on the linear footage of the takeoff, waler run variable and snap tie spacing

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Concrete (Optional) - calculated using the takeoff total
    • Rebar Vertical Reinforcing - available by the foot or pound, calculated using wall dimensions, spacing variable and mat count
    • Rebar Horizontal Reinforcing - available by the foot or pound, calculated using wall dimensions, spacing variable and bar lap count
    • Form Panels (Optional) - calculated using wall dimensions
    • Add For Waler Brackets - calculated using the length of the wall and waler bracket variable
    • Snap Ties (optional) - calculated using the length of the wall, snap tie spacing and waler bracket variables
    • Form Crew - requires the productivity variable to calculate
    • Concrete Placing Crew - requires the productivity variable to calculate
    • Anchor Bolts (optional) - calculated using the length of the wall and anchor bolt spacing variable
    • Waterstop (Optional) - equals the length of the wall
    • Rebar Crew In Pounds of Steel - requires the productivity variable to calculate

    Continuous Footer - Linear

    Summary: This assembly is designed for a Linear takeoff and offers continuous, transverse, vertical and stirrup rebar

    Variables:

    • Footer Width In - used to calculate concrete volume and transverse rebar
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Continuous Rebar Count - the number of rebar runs going along the length of the footing
    • Horizontal Rebar Spacing In - used to calculate horizontal/transverse rebar
    • Vertical Dowel Spacing In - used to calculate vertical dowels
    • Vertical Dowel Length Ft - the total length of one vertical dowel, including any bends, J's or hooks
    • Excavate Production Lf Per Hr - the productivity rate of the crew you chose
    • Place Production Cy Per Hr - the productivity rate of the crew you chose
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Depth To Top Of Footer In - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Footer Depth In - the vertical dimension of the footing
    • Cont Bar Size - the number of rebar you chose
    • Cross Bar Size - the number of rebar you chose
    • Vert Dowel Size - the number of rebar you chose
    • Crew Production Lbs Per Hr - the productivity rate of the crew you chose
    • Stirrup Spacing In Feet - used for calculating stirrup rebar
    • Stirrup Length In Feet - total length of one stirrup piece

    Required Items:

    These items will be added without having to choose them

    • Foundation, Linear Feet - summary item reflecting the linear takeoff total
    • 16 Gauge Tie Wire - calculated using the rebar totals and size variables
    • Foundation, Square Feet - summary item reflecting the area of the footing when viewed from above
    • Excavation Quantity - total amount of dirt excavated calculated using footing volume and depth to top of footer variable

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff total and dimension variables
    • Rebar Continuous Reinforcing - by the foot or pound, calculated using linear takeoff total, rebar count variable and bar lap count
    • Rebar Cross-Bridging (IF USED) - transverse rebar by the foot or pound, calculated using linear takeoff total, rebar spacing variable and footing width variable
    • Add Rebar Chairs - one chair per continuous rebar count spaced at 4 feet
    • Add Rebar Vertical Dowels - by the foot or pound, calculated using linear takeoff total, length and spacing variables
    • Excavation Crew By linear Feet Of Trench - requires the productivity variable to calculate
    • Rebar Crew By Pounds Of Steel - requires the productivity variable to calculate
    • Concrete Placing Crew - requires the productivity variable to calculate
    • Rebar Stirrups (IF USED) - by the foot or pound, calculated using the linear takeoff total, length and spacing variables

    Continuous Footer, Earth Formed - 3D

    Summary: This assembly is requires a Volume 3D takeoff and offers continuous, transverse, vertical and stirrup rebar

    Variables:

    • Footer Width In - used to calculate horizontal/transverse rebar
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Continuous Rebar Count - the number of rebar runs going along the length of the footing
    • Horizontal Rebar Spacing In - used to calculate horizontal/transverse rebar
    • Vertical Dowel Length Ft - used to calculate vertical rebar
    • Excavate Production Lf Per Hr - the productivity rate of the crew you chose
    • Reinforcing Production Lf Per Hr - the productivity rate of the crew you chose
    • Place Production Cy Per Hr - the productivity rate of the crew you chose
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Depth To Top Of Footer In - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Cont Bar Size - the number of rebar you chose
    • Cross Bar Size - the number of rebar you chose
    • Vert Dowel Size - the number of rebar you chose
    • Vertical Dowel Spacing In - used to calculate vertical dowels
    • Crew Production Lbs Per Hr - the productivity rate of the crew you chose
    • Excavation Production Cy Per Hour - the productivity rate of the crew you chose
    • Stirrup Spacing In Feet - used to calculate stirrups

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire - calculated using the rebar totals and size variables
    • Foundation, Linear Feet - summary item reflecting the linear takeoff total
    • Foundation, Square Feet - summary item reflecting the area of the footing when viewed from above
    • Excavation Quantity - total amount of dirt excavated calculated using footing volume and depth to top of footer variable

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Select Concrete - calculated using the takeoff volume total
    • Add Continuous Reinforcing - by the foot or pound, calculated using linear takeoff total, rebar count variable and bar lap count
    • Add Rebar Cross-Bridging (IF USED) - transverse rebar by the foot or pound, calculated using linear takeoff total, rebar spacing variable and footing width variable
    • Add Rebar Chairs - one chair per continuous rebar count spaced at 4 feet
    • Add Rebar Vertical Dowels - by the foot or pound, calculated using linear takeoff total, length and spacing variables
    • Excavation Crew Per linear Feet Of Trench - requires the productivity variable to calculate
    • Reinforcing Crew Per linear Feet Of Trench - requires the productivity variable to calculate
    • Concrete Placing Crew - requires the productivity variable to calculate
    • Reinforcing Crew per Pound - requires the productivity variable to calculate
    • Excavation Crew Per CY - requires the productivity variable to calculate
    • Rebar Stirrups (IF USED) - by the foot or pound, calculated using the linear takeoff total, length and spacing variables

    03 33 13 - Slab On Grade

    Concrete Building Slab On Grade - 2D

    Summary: This assembly requires a Volume 2D takeoff and yields concrete, aggregate base, and WWM reinforcing. Rebar must be added using a separate assembly.

    Variables:

    • Base Depth In - used to calculate aggregate base
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
    • Finish Grade Production Sf Per Hr - the productivity rate of the crew you chose
    • Reinforcing Chairs Sq Ft Per Ea - the square foot spacing of rebar chairs

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff volume
    • Choose If Using WWM Reinforcing - calculated based on the square footage from the takeoff
    • Add Aggregate Base If Required - calculated using square footage from the takeoff and the base depth variable
    • Add Vapor Barrier If Required - calculated using the square footage from the takeoff
    • Add For Fibrous Reinforcing - based on the volume from the takeoff
    • Choose Finish - summary or labor items reflecting the square footage of the takeoff
    • Choose Crew For Place & Finish - requires the productivity variable to calculate
    • Choose Crew For Finish Grade Work - requires the productivity variable to calculate
    • Rebar Chairs - calculated using the area from the takeoff and spacing variable

    Concrete Paving On Grade - 2D

    Summary: This assembly requires a Volume 2D takeoff and yields concrete, aggregate base, and WWM reinforcing. Rebar must be added using a separate assembly.

    Variables:

    • Base Depth In - used to calculate aggregate base
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
    • Finish Grade Production Sf Per Hr - the productivity rate of the crew you chose

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff volume
    • Choose If Using WWM Reinforcing - calculated based on the square footage from the takeoff
    • Add Aggregate Base If Required - calculated using square footage from the takeoff and the base depth variable
    • Add Vapor Barrier If Required - calculated using the square footage from the takeoff
    • Add For Fibrous Reinforcing - based on the volume from the takeoff
    • Choose Finish - summary or labor items reflecting the square footage of the takeoff
    • Choose Crew For Place & Finish - requires the productivity variable to calculate
    • Choose Crew For Finish Grade Work - requires the productivity variable to calculate

    Concrete Sidewalk On Grade - 2D

    Summary: This assembly requires a Volume 2D takeoff and yields concrete, aggregate base, and WWM reinforcing. Rebar must be added using a separate assembly.

    Variables:

    • Base Depth In - used to calculate aggregate base
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
    • Finish Grade Production Sf Per Hr - the productivity rate of the crew you chose

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff volume
    • Choose If Using WWM Reinforcing - calculated based on the square footage from the takeoff
    • Add Aggregate Base If Required - calculated using square footage from the takeoff and the base depth variable
    • Add Vapor Barrier If Required - calculated using the square footage from the takeoff
    • Add For Fibrous Reinforcing - based on the volume from the takeoff
    • Choose Finish - summary or labor items reflecting the square footage of the takeoff
    • Choose Crew For Place & Finish - requires the productivity variable to calculate
    • Choose Crew For Finish Grade Work - requires the productivity variable to calculate

    03 33 19 - Elevated Concrete

    Concrete Stair Pans - 2D

    Summary: This assembly requires a Volume 2D takeoff and only concrete, labor and a square foot summary.

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff volume
    • Choose Finish - summary or labor items reflecting the square footage of the takeoff
    • Choose Crew For Place & Finish - requires the productivity variable to calculate

    Elevated Concrete Beam - 3D

    Summary: This assembly requires a Volume 3D takeoff and offers continuous and stirrup rebar.

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Stirrup Spacing In - used to calculate stirrups
    • Beam Width In - the horizontal dimension (along with the length from the takeoff) of the beam, used to calculate stirrups
    • Beam Depth In - the vertical dimension of the beam, used to calculate stirrups
    • Continuous Rebar Count - how many runs of rebar go along the length of the beam
    • Formed Side Count - how many side of the beam need forms
    • Form Production Lf Per Hr - the productivity rate of the crew you chose
    • Place Production Cy Per Hr - the productivity rate of the crew you chose
    • Rebar Waste 1 To 100 - enter a percentage waste factor
    • Rebar Stock Length Feet - the length of rebar you typically order
    • Bar Lap Count - See Terminology section for a description
    • Stirrup Bar Size - the number of rebar you chose
    • Crew Production Lbs Per Hr - the productivity rate of the crew you chose
    • Cont Bar Size - the number of rebar you chose

    Required Items:

    These items will be added without having to choose them

    • 16 Gauge Tie Wire - calculated based on the takeoff volume
    • Elevated Concrete Beam - Summary item reflecting the linear component of your takeoff
    • Shoring Jack - one every 4 feet of takeoff length

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff volume
    • Continuous Rebar - by the foot or pound, calculated using linear takeoff total, rebar count variable and bar lap count
    • Rebar Stirrups - by the foot or pound, calculated using beam dimensions and spacing variables
    • Add Form Panels - calculated using the linear footage from the takeoff and side count variable
    • Form Crew In Linear Feet per Hour - requires the productivity variable to calculate
    • Rebar Crew In Pounds Per Hour - requires the productivity variable to calculate
    • Concrete Placing Crew In Cubic Yards Per Hour - requires the productivity variable to calculate

    Elevated Concrete Slab - 2D

    Summary: This assembly requires a Volume 2D takeoff. Rebar is not included, so use a separate assembly if needed.

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - calculated using the takeoff volume
    • Choose If Using WWM Reinforcing - based on the area component of the takeoff
    • Add For Fibrous Reinforcing - based on the volume of the takeoff
    • Choose Finish - summary or labor items reflecting the square footage of the takeoff
    • Choose Crew For Place & Finish - requires the productivity variable to calculate

    03 47 00 - Site Cast Concrete

    Lift-Slab Concrete - 2D

    Summary: This assembly requires a Volume 2D takeoff

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Form Production Sf Per Hr - the productivity rate of the crew you chose
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
    • Erection Production Sf Hr - the productivity rate of the crew you chose

    Required Items:

    These items will be added without having to choose them

    • Form Release, Wood Forms - calculated using the area from the takeoff

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on the volume from the takeoff
    • Choose Form Crew - requires the productivity variable to calculate
    • Choose Place & Finish Crew - requires the productivity variable to calculate
    • Choose Erection Crew - requires the productivity variable to calculate

    Tilt-Up Concrete - 2D

    Summary: This assembly requires a Volume 2D takeoff

    Variables:

    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Form Production Sf Per Hr - the productivity rate of the crew you chose
    • Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
    • Erection Production Sf Hr - the productivity rate of the crew you chose

    Required Items:

    These items will be added without having to choose them

    • Form Release, Wood Forms - calculated using the area from the takeoff

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on the volume from the takeoff
    • Choose Form Liner - equal to the area from the takeoff
    • Choose Form Crew - requires the productivity variable to calculate
    • Choose Place & Finish Crew - requires the productivity variable to calculate
    • Choose Erection Crew - requires the productivity variable to calculate

    32 16 00 - Curbs & Gutters

    Curb With Gutter, "L" Shaped - Linear

    Summary: This assembly is designed for a Linear takeoff. There is no rebar included.

    Variables:

    • Gutter Width In - horizontal dimension used to calculate the gutter portion of concrete
    • Curb Height In - vertical dimension used to calculate the curb portion of concrete
    • Gutter Depth In - vertical dimension used to calculate the gutter portion of concrete
    • Concrete Waste Percentage - enter a percentage waste factor
    • Base Stone Width In - horizontal dimension used to calculate aggregate base
    • Base Stone Depth In - vertical dimension used to calculate aggregate base
    • Form Production Lf Per Hr - the productivity rate of the crew you chose
    • Place Finish Production Lf Per Hr - the productivity rate of the crew you chose
    • Grading Production Lf Per Hr - the productivity rate of the crew you chose
    • Curb Width In - horizontal dimension used to calculate the curb portion of concrete

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on the linear footage from the takeoff and curb dimension variables
    • Choose Curb Type - offers summary items describing the curb and reflecting the linear footage from the takeoff
    • Add Aggregate Base Stone - calculated using Linear takeoff total and stone dimension variables
    • Choose Grading Crew - requires the productivity variable to calculate
    • Choose Form Crew - requires the productivity variable to calculate
    • Choose Place & Finish Crew - requires the productivity variable to calculate

    Flush Curb - Linear

    Summary: This assembly is designed for a linear takeoff

    Variables:

    • Curb Width In - one horizontal dimension of the concrete
    • Curb Height In - the vertical dimension of the concrete
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Stone Base Depth In - used to calculate aggregate base
    • Grade Production Lf Per Hr - the productivity rate of the crew you chose
    • Form Production Lf Per Hr - the productivity rate of the crew you chose
    • Place Finish Production Lf Per Hr - the productivity rate of the crew you chose

    Required Items:

    These items will be added without having to choose them

    • DOT Flush Curb & Gutter - a summary item reflecting the linear footage from the takeoff

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on the linear footage from the takeoff and curb dimension variables
    • Add Aggregate Base Stone - calculated using Linear takeoff total and stone depth variable
    • Choose Grading Crew - requires the productivity variable to calculate
    • Choose Form Crew - requires the productivity variable to calculate
    • Choose Place & Finish Crew - requires the productivity variable to calculate

    Vertical Curb, Box Shaped - Linear

    Summary:

    Variables:

    • Curb Width In - one horizontal dimension of the concrete
    • Curb Height In - the vertical dimension of the concrete
    • Concrete Waste 1 To 100 - enter a percentage waste factor
    • Stone Base Depth In - used to calculate aggregate base
    • Grade Production Lf Per Hr - the productivity rate of the crew you chose
    • Form Production Lf Per Hr - the productivity rate of the crew you chose
    • Place Finish Production Lf Per Hr - the productivity rate of the crew you chose

    Required Items:

    These items will be added without having to choose them

    • Box Curb - a summary item reflecting the linear footage from the takeoff

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Choose Concrete - based on the linear footage from the takeoff and curb dimension variables
    • Add Aggregate Base Stone - calculated using Linear takeoff total and stone depth variable
    • Choose Grading Crew - requires the productivity variable to calculate
    • Choose Form Crew - requires the productivity variable to calculate
    • Choose Place & Finish Crew - requires the productivity variable to calculate

    Concrete Formwork - 2D

    Summary: This assembly will work with any linear or area-based takeoff, but is best suited for areas.

    Variables:

    • Stake Spacing In Feet - required to calculate the stakes items

    Required Items:

    There are no required items in this assembly

    Item Groups:

    These groups contain a selection of items that must be chosen if required

    • Group 2 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board
    • Group 1 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board
    • Stakes - calculated using the linear perimeter of the takeoff and stake spacing variable

    Concrete Formwork - Linear

    Summary: This assembly will work with any linear or area-based takeoff but is best suited for linear-type takeoffs like continuous footings and beams.

    Variables:

    • Stake Spacing In Feet - required to calculate the stakes items

    Required Items:

    There are no required items in this assembly.

    Item Groups:

    These groups contain a selection of items that must be chosen if required.

    • Group 2 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board and multiplying by 2
    • Group 1 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board and multiplying by 2
    • Stakes - calculated using the linear perimeter of the takeoff and stake spacing variable

    Was this article helpful?